PostPosted: Thu Mar 04, 2010 8:30 am    Post subject: Groups and Resource explained. Reply with quote

Groups and Resource explained.

Up to and including version 5, Resources, Equipment and Contacts were all separated which restricted many possibilities for reporting and filtering. Since version 6 these are all now combined as Resources.

Groups and Resources are the key to powerful filtering and reporting so we thought it was time to describe how they can be used. Although they are called Groups and Resources this description probably doesn't describe how powerful they can be.

Groups are a collection of Resources. It possible to set a group as mandatory, so for example when creating an event you MUST select a resource from the Task group and Charge Type group otherwise the event will not be saved.

Groups can also set the labels for any of its resource, E.g. If you have a resource in a group called Staff may want fields for, Name, Address, Title and Post Code etc, A group called Equipment may want fields for Name, Serial Number, Type etc, A group called Servers may want fields for Server Name, Location, Operating system.

A resource can not only be a room, person or machine, but could also just be a tag such as Busy, Free, Booked or Available. They can also be used to specify a charge type, costs, working hours, and much much more.

Once you have linked an event to a resource all the outputs, reports, and charts can be set to filtered by your chosen resources giving you an unlimited number of possibilities for views, reports and outputs.


An example of a event using many resources from many groups...

Event:
- Training Course for 5 days
Linked Resources:
- Room1 (From a Rooms group)
- Tutor (From a Staff group)
- Internet Equipment (from an Equipment group)
- 10 x Chairs (from an Equipment group)
- Charge Code Full (from Charges group - Mandatory)
- Task Busy (from a Task group - Mandatory)
- Working Hours (from a Working hours group - Mandatory)

Please let us know if you need more information.
_________________
Regards

Mark - Schedule it Ltd
http://www.scheduleit.co.uk
http://www.scheduleit.co.uk/online/
Back to top
View user's profile Send private message Visit poster's website
Display posts from previous:   
Post new topic   Reply to topic    Schedule it Forum Index -> How do I... All times are GMT
Page 1 of 1

 
Jump to:  
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum



Copyright © 2003-2010 Schedule it Ltd. All rights reserved. Returns Policy | Terms